Civil Construction Works for a Fertiliser Warehouse at Periam, TImis County
Date of issue: Oct.2012 - Feb.2013
Project value: 1,200,000.00 €
The warehouse is a rectangular shaped building with dimensions 135.7m X 30m,
4225 square meters built area and maximum height of 8.53 m, maximum height of
storage products being 3,50m inside the hall
On the parcel in question, divided prefabricated containers with a total built area of 42.45 square meters
will be placed in order to fulfill administrative functions and their annexes such a : offices, bathroom,
cloakroom, kitchen, meeting room, guardian booth.
Built a depot for forklifts with built area 34.20 square meters

Execute a traffic and pedestrian platforms with a total area of 4366.10 square meters,
in order to develop safe road traffic, as the client wishes
Execute a fence with welded mesh fence and with auto access - 820 meters

Building office space in molding area - Yazaki Components Technology - Arad

 

Date of issue: July.2012 -Sept.2012
Project value: 40,000.00 €

 

Build an office area on a surface of 120 sm

Executin of PVC windows and doors with 45 minutes fire resistant on a surface of 22 sm

Execution of metal ladder with 60 minutes fire resitant

Building concrete platform - Hella Romania - Lugoj, Timis

 

Date of issue: July.2012 -August.2012
Project value: 45,000.00 €

 

Building concrete platform 850 sm

Execution works at the “Hall - Spaces for adhesive mixing and gun washing“ - Takata, Arad

 

Date of issue: May 2012 - July 2012
Project value: 60,000.00 €

 

Expanded built area of 122.80 sm

The building is made of a mixed structure of masonry and reinforced concrete

The foundations are made of concrete and reinforced concrete

The walls are made of full bricks with a thickness of 37.5 cm, respectively 25 cm

The floor is made of reinforced concrete

Infrastructure and superstructure design and execution works - Extension of Mahle Hall, Phase IV - Timisoara

 

Date of issue: April 2012 - June 2012
Project value: 350,000.00 €

 

Execution of insulated foundations of monolith reinforced concrete and prefabricated collars

Execution of earthworks on a surface of 3200 sm

Montage of prefabricated elements (superstructure) on a surface of 3200 sm

Execution of bases and docking systems made of monolith reinforced concrete

Infrastructure and superstructure design and execution works - Extension of Mahle Hall, Phase III

 

Date of issue: Oct. 2011 - Dec. 2011
Project value: 295,000.00 €

 

Execution of insulated foundations of monolith reinforced concrete and prefabricated collars

Execution of earthworks on a surface of 3200 sm

Montage of prefabricated elements (superstructure) on a surface of 3200 sm

Execution of bases and docking systems made of monolith reinforced concrete